SNELL ROAD (JACKSON STREET TO MOSER STREET) RECONSTRUCTION &
NORTH MAIN STREET STORM SEWER CONSTRUCTION (SNELL TO 2000’ SOUTH)
The reconstruction of Snell Road and the construction of storm sewer on North Main Street is anticipated to begin on or about *May 11thweather dependent. The work under this Contract consists of the public construction of concrete pavement and sidewalk on Snell Road, along with storm sewer, sanitary sewer, water main relay, and electrical work. The relay of storm sewer along North Main Street, along with replacing the concrete pavement, is also included. Although no city contract work will occur on Snell Road until the storm sewer is completed, Snell Road access will be impacted by private utility work and construction staging.
*Erosion Control/Traffic Control/Construction Staging/Saw cutting preparations may begin the week of May 11th.
Phase 1 – North Main Street (Snell to 2000’ South (May11th))
· Construction Window = Eight (8) Consecutive Weeks.
· Work anticipated to be completed mid-July.
Phase 2 – Snell Road (Jackson Street to the east radius of North Main Street (mid-July))
· Construction Window = Fourteen (14) Consecutive Weeks.
· Work must be completed by Friday, October 30, 2020.
· All work, including utilities, laterals, pavement, sidewalk, driveways, and restoration, must be completed within the Construction Window, and the section must be fully opened up to traffic.
Phase 3 – Snell Road (East radius of North Main Street to Moser (mid-July))
· Construction Window = Thirteen (13) Consecutive Weeks.
· Work must be completed by Friday, October 30, 2020.
· All work, including utilities, laterals, pavement, sidewalk, driveways, electrical, and restoration, must be completed within the Construction Window, and the section must be fully opened up to traffic.
Please forward on to all parties that may have an interest in this project. Thank you and don’t hesitate to reach out with questions or concerns.
All work is weather dependent.